WILLIAMSBURG, Ohio — Jackson Township will begin its 2026 road paving program Tuesday, with crews working through the end of the month on repairs to Monterey Road, Monterey Maple Grove Road and Richey Road, the township said in a Facebook post.

The township apologized for the late notice, saying a recent storm forced last-minute adjustments to the project timeline.

Full-depth repairs on Monterey Road and Monterey Maple Grove Road are scheduled for Tuesday, according to the township. Crews will then pave Monterey Maple Grove Road from State Route 50 to Caudill Road on Wednesday, followed by paving on Richey Road on Thursday. The work will wrap up Aug. 31 with a parking lot expansion at the township’s firehouse and maintenance facility.