PIERCE TOWNSHIP, Ohio — Road crews will rebuild and repave five residential streets in Pierce Township during the week of July 20, with the heaviest work concentrated Wednesday through Friday, the township said in a post outlining its 2026 paving schedule.

No paving is scheduled in the township Monday, July 20, or Tuesday, July 21, according to the township. Full-depth repairs are planned for Wednesday, July 22, on Grouse and Wood Duck. On Thursday, July 23, crews will shift to surface paving on Red Bud, Grouse, Wood Duck and E. Legendary. Surface paving on Twig is set for Friday, July 24.

Full-depth repairs and surface paving are different stages of the same job. Full-depth work removes and rebuilds a damaged section of the roadbed, while surface paving lays a fresh top layer of asphalt over the existing base. Several of the streets on the schedule are slated for both, with the base repairs completed before the new surface goes down.